Scope of Work and Project Timeline
Fort Montgomery Elementary School Alterations
$5,177,353 (includes escalation)
- Updating the school’s building management system, a computer-based control system that needs to be installed within buildings to monitor and regulate the building's electrical equipment, lighting and ventilation
- Updating plumbing fixtures in the bathrooms in the ‘93 wing
- Enhancing the building’s main entrance to ensure accessibility for all visitors
- Installing a two-sided elevator to ensure accessibility for all visitors
- Installing a wheelchair accessible ramp past the lower level stairs
- Replacing all older electrical panels which are past their useless life
- Replacing hot water pump and air separation systems
- Replacing classroom unit ventilators and adding air conditioning
- Replacing the cafeteria’s air handling unit
- Replacing various light fixtures
Fort Montgomery Elementary School Additions
$6,448,087 (includes escalation)
- Creating a new, larger multipurpose room (gymnasium/cafeteria) with a warming kitchen
- Renovating the existing multipurpose room to create a Library-Media Center as well as learning spaces for classrooms that are currently displaced, such as art, music, and some instructional support services.
- Renovating the existing kitchen area to create a new, larger health office for the nurse.
Highland Falls Intermediate School Alterations
$11,559,079 (includes escalation)
- Updating the school’s building management system, a computer-based control system that needs to be installed within buildings to monitor and regulate the building's electrical equipment, lighting and ventilation
- Reconstructing the main parking lot and replacing its insufficient draining system
- Replacing areas of the roof that are lifting up, sinking down and/or are letting water seep through
- Installing air conditioning in the kitchen and areas of the basement
- Upgrading various antiquated heating and cooling systems
James I. O’Neill High School Alterations
$14,296,330 (includes escalation)
- Updating the school’s building management system, a computer-based control system that needs to be installed within buildings to monitor and regulate the building's electrical equipment, lighting and ventilation
- Renovating the kitchen, replacing 30+ year old equipment and updating its plumbing
- Replacing areas of the roof on both the A-Wing and the B-Wing that are lifting up, sinking down and/or are letting water seep through
- Installing air conditioning to the gymnasium’s rooftop unit and various classrooms
- Upgrading various heating and cooling systems and electrical panels to correct the uneven temperatures throughout the building
Referendum at-a-glance
- Project total: $44,435,600
- Portion covered by state aid: 82.9% (for every $100 of aidable work, the district will receive $82.90 back)
- Portion covered by capital reserve: $8,810,000
- Portion covered by debt reserves: $755,287
- Additional borrowing from residents: $0
Proposed capital project timeline
- Community vote: March 2023
- Design development and review: Spring-Summer 2023
- NYSED review and approval process: Fall-Winter 2023
- Bidding period: Winter-Spring 2023/2024
- Award of contracts: By Spring 2024
- Construction phase: Summer 2024-Fall 2025
- Project completion: By November 2025